ARCHSPLACE
Architecture, made simple — since 2018
Plumbing point

PlanHin the studio

Plumbing point

Plumbing point places a supply or a waste point with one click, on a wall or in a room's floor. The pipes are not drawn by hand: the supply runs from the manifold or the meter and the drains to the nearest stack are laid by themselves.

What it is

Plumbing point places the points of the plumbing: where water comes in and where it leaves. The list beside the tools offers your template's points; in a project under the US template, for example, cold and hot water stub-outs, a shutoff valve, a PEX manifold, a hose bibb, the wastes of a water closet, a lavatory, a bidet, a kitchen sink, a shower, a bathtub, a clothes washer and a dishwasher, waste drains of several sizes, a building drain, a floor drain, a vent through the roof and a downspout. The water meter has a tool of its own.

The pipes follow by themselves. The supply is a star: every cold and hot point gets its own run from the nearest manifold, or from the meter when there is none, through the floor and up its wall. Each level's waste points drain to the nearest drain stack, in one network laid with its slope and fittings. Nothing of it is stored: move a point and the pipes are laid again. They show with the Plumbing overlay.

When to use it

  • Placing the supply and waste points of a bathroom, a kitchen or a laundry.
  • Adding a floor drain to a shower or a garage.
  • Checking the network the studio lays as you add points.

The steps

  1. Take the tool. Press H, or click the Plumbing button. The status bar says to click a wall or inside a room.

    Plumbing armed with the Plumbing overlay ticked under Disciplines: the drop button is lit among the drawing tools, its name Plumbing (H), with the other plumbing tools under the triangle, is under the hand, and the status bar says to click a wall or inside a room.
  2. Choose the point. Pick it in the list beside the tools.

    The list set to Hot water stub and the hand on the bathroom's east wall: a dashed circle with the point's glyph follows the hand on the wall, and the status bar names the point on line.
  3. Click where it stands. A supply point, a valve or a manifold stands on a wall: click on the wall or within about 60 cm (2 ft) of it, on the side it faces. A floor drain stands in a room: click inside the room. A waste point goes where you click: within about 45 cm (18 in) of a wall it stands on that wall, farther away it stands in the floor of the room you clicked in.

    The click made: the hot water point stands on the east wall with its mark and its dashed run beside it; the outliner counts one device and the History in the status bar lists one row, Place a device, with the tool still in hand.
  4. Adjust it in its panel. Select the point with Select to set its mounting height, and read what its pipes could not do, if anything.

    The point taken with Select: EL-001 is lit in the outliner, its panel shows its kind SUPPLY_HOT and its mounting height, 1'-9", and a Plumbing section below says its pipe size and that no manifold or meter feeds it.

What it refuses

  • A wall point far from every wall. Farther than about 60 cm from any wall, nothing is placed.
  • A floor point outside a room. Outside every room the walls enclose, a message says to click inside a room, and nothing is placed.
  • The same point twice. A point of the same kind on the same face of the same wall, within 5 cm of one already there, is refused with a message: place it beside it.
  • A point where no pipe can reach. The project flags a point set in an opening or over a hole in the floor, and says on its panel when its pipe had to cross a hole, a column, a beam or an opening.

What it writes to the contract

One new device entry at the end of the project's list of devices, as one step that one undo takes back: its kind, and either its wall, its distance along it and its face, or its room and its point in the floor, with the phase the view draws in. The pipes, their diameters, slopes and fittings are never written: they are worked out from the points each time the project is built.

Concepts

Common questions

Is placing a WC enough to get its drain?

No. A fixture is architecture and connects to nothing. The plumbing starts at its points: place the WC's waste point, and its cold water point, with this tool.

Where do the drains go?

Each level's waste points drain to their nearest drain stack, laid in one network with its slope and fittings. Place at least one stack with the Drain stack tool.

Does a waste point go in the wall or in the floor?

It goes where you click: within about 45 cm (18 in) of a wall it stands on that wall, farther away it stands in the floor of the room.