A template switch moves a project already drawn from one country template to another, such as from ISO to ABNT. Before anything changes, a dialog lists what the project keeps as its own, what follows the new template from now on, and what the new rules refuse or rebuild; Switch applies it as one change, which one undo takes back.

What it is

A project is designed under one template, the drawing standard of a country or the international one, and can switch to another at any time. The switch starts in the standard panel, opened from the standard's key in the status bar: choose another standard in Designed under. The assistant may propose a switch too, and it goes through the same dialog.

Before anything changes, a dialog asks Switch the project to and the new template. Under its title it says that the project leaves the old template for the new one, that every element you drew keeps its build-up, its size and its place, and that the new template's rules and drawing conventions apply from now on. Then it lists, only where there is something to list:

  • Kept as the project's own: each wall type, slab type, opening family, material, pattern, room use, phase or other entry the project uses that the new template does not have, or builds differently, marked not in or different in the new template, with the elements that use it. They keep the old template's version as the project's own; what you draw from now on uses the new template's.
  • Following the new template from now on: the entries the new template defines differently as its own conventions, its symbols, hatches and sizing, with the elements they apply to. Devices and pipes keep the height and the size they have.
  • Defaults the project keeps: the exterior wall, interior wall, floor, slab on grade, strip footing and spread footing that elements naming no type use. The project keeps the old template's, so those elements stay as they are; each row says what the new template would use instead.
  • Refused under the new template: the elements its own rules refuse. They stop being built, stay in the file, and come back once they meet the rule.
  • Rebuilt by the new template's rules: what comes from the rules rather than from your drawing, such as a stair's riser height, a slab's thickness or a footing's width and depth, each with its value before and after.
  • The patterns that leave with the old template, and the project's own patterns, kept.

When nothing is lost, the dialog says so in one line: everything the project uses is the same in the new template.

Switch to and the new template applies the switch; Cancel changes nothing.

When to use it

  • A project started on the international template, now built in a country with a template of its own.
  • A project moved to another country, to be drawn under its practice.
  • Checking what a project would become under another standard, before deciding.

The steps

  1. Open the standard panel. Click the standard's key in the status bar, such as ISO. The standard panel opens in the left column.

    The standard's key ISO pressed in the status bar: the standard panel is open in the left column with Norm, Patterns, Installations, Text heights and Pens, over the plan of a house on two levels.
  2. Choose the new template. Open Norm, and in Designed under choose ABNT. The dialog Switch the project to ABNT? opens.

    ABNT chosen in Designed under: the dialog Switch the project to ABNT? says the project leaves ISO for ABNT and begins its list Kept as the project's own, with the wall types, slab types and opening families it keeps, and the buttons Cancel and Switch to ABNT.
  3. Read what changes. Read the lists: the types kept as the project's own, with the walls that use them, the defaults the project keeps, and what ABNT's rules rebuild, such as a footing's depth.

    The dialog read down to its end: Defaults the project keeps, Rebuilt by ABNT's rules with a footing's depth going from 450 mm to 600 mm and a slab's type changing, then Patterns that leave with ISO and The project's own patterns, kept.
  4. Switch. Click Switch to ABNT. The status bar's key reads ABNT, and every drawing follows ABNT's conventions.

    After Switch to ABNT the status bar's key reads ABNT, the standard panel says Designed under ABNT, Brazilian practice, and the plan is drawn with ABNT's dimension style.
  5. Undo if needed. Press Ctrl+Z: the project is back under ISO, as it was, in one step.

    After Ctrl+Z the key reads ISO again and the panel is back on ISO, international standards, with the plan as it was.

What it refuses

  • A switch to the template the project is already under. Nothing is asked and nothing changes.
  • Elements the new rules refuse. They are listed before you switch, then stop being built, staying in the file until they meet the rule.

What it writes to the contract

One change. standard names the new template; a standard of your library is also embedded as standardTemplate. Each entry kept as the project's own is written into the project's own catalogs (wallTypes, slabTypes, patterns, openingFamilies, deviceKinds, fixtureKinds, pipeSystems), marked with the template it came from. A type the new template builds differently is copied under a new id that adds the old template's key, and the elements that use it are pointed at the copy. The defaults kept are written as the project's own defaults, and words the new template lacks join the project's vocabularies. Nothing you drew moves or changes size.

Common questions

Will my walls change when I switch the template?

No. Every element you drew keeps its build-up, its size and its place. A wall type the new template lacks, or builds differently, is kept in the project as its own, so the walls that stand keep it, while what you draw afterwards uses the new template's types.

What does change?

The new template's rules and drawing conventions: its symbols, hatches and sizing for devices, fixtures, pipe systems and patterns, its code rules, and what is derived from the rules, such as stairs, slabs, roofs and footings, which are rebuilt by them. The dialog lists each of these before you switch.

Can I switch back?

Yes. Undo takes the switch back in one step, and switching back to the first template later makes the project follow it again.